Isometric cutaway model of the Boeing X80 Annexe refurbishment in Farnborough, showing the office floor layout designed by Salvis
Isometric cutaway model of the Boeing X80 Annexe refurbishment in Farnborough, showing the office floor layout designed by Salvis

Boeing X80 ANnexe

Defence

Client
Brenmar
End client
Boeing (UK) Ltd
Sector
Aerospace / Defence
Location
Cody Technology Park, Farnborough
Project
Three-storey refurbishment and fit-out
Services
M&E services design, IES-VE thermal modelling, ventilation, water services and electrical infrastructure

Who worked on this project

Mike Keating
Mike Keating
Director of Engineering
View profile →

M&E refurbishment design

Brenmar appointed Salvis to deliver the M&E design for the major refurbishment and fit-out of the Boeing X80 Annexe, an existing three-storey building at Cody Technology Park, Farnborough. Salvis was involved from RIBA Stage 3 through to completion. The building fabric and services had a backlog of repair issues, so the aim was a full refurbishment, fit for future occupants.

Internal layouts were reconfigured across all three floors, with workshops and a loading bay on the ground floor and offices on the first and second floors. Salvis surveyed the existing services, modelled the building in IES-VE, and designed VRF heat-pump heating and cooling, ventilation, water services, drainage and the electrical services.

Scope of services

  • Survey of existing mechanical services.
  • IES-VE thermal modelling.
  • Heating and cooling load calculations.
  • Space heating and cooling design.
  • Mechanical ventilation.
  • Domestic hot and cold water services.
  • Above-ground drainage.
  • Drawings, equipment schedules and technical submissions.
  • Electrical services design and design coordination.

Key systems

  • VRF heat-pump heating and cooling.
  • Heat-recovery ventilation.
  • New LV distribution system.
  • Integrated BMS and controls.
  • UPS for critical equipment.
  • Services for workshop, 3D printing and office areas.

Challenges

  • Refurbishing ageing building infrastructure
  • Combining workshop and office environments
  • Understanding heating and cooling requirements
  • Coordinating mechanical and electrical services

Lessons learned

01Model the refurbished building before sizing plant

IES-VE modelling gave calculated heating and cooling loads to design from, rather than relying on the capacity of the equipment being replaced.

02Mixed-use facilities need coordinated services

A ground-floor workshop with two floors of offices above meant the design had to serve very different areas within one building.

03Refurbishment is more than replacing equipment

The project reconfigured all three floors alongside wider services upgrades, rather than swapping out individual plant items.

04Build resilience into the services strategy

BMS and UPS systems were designed in alongside the HVAC and electrical infrastructure to support the specialist workshop and office areas.