Air conditioning units in a purpose-built external plant enclosure designed and installed by Salvis

Southfield plant replacement

NHS Healthcare

3 Mitsubishi ASHPs Installed
1000L AO Smith Buffer Vessel
17.59% Increase in kW Capacity
100% Electric Heating Transition

Plant Replacement Plan.

Southfield Hospital required a reliable, energy-efficient replacement for their ageing gas-fired boilers. We installed a complete Mitsubishi air source heat pump system, supported by a 1000L AO Smith buffer tank, new pipework, controls, and electrical integration.

The Challenge:

The existing gas-fired boilers (2x Hamworthy Warmwell, 54 kW each, installed 2004) had suffered recent failures, showed corrosion, lacked proper safety relief valves, and the secondary pump was suspected to be oversized.

A reliable, modern heating solution was urgently needed to restore system integrity, improve efficiency, and ensure uninterrupted comfort for the hospital.

The Solution:

We replaced the outdated gas boiler heating plant with a fully electric air-source heat pump system using Mitsubishi units and a 1000 litre AO Smith buffer. The project was successfully delivered within a 5-week programme and included:

A full plant room strip-out of the legacy 2004 equipment.
Installation of three high-efficiency Mitsubishi air source heat pumps.
Integration of a 1000L AO Smith buffer vessel.
Fitting of entirely new LTHW (Low Temperature Hot Water) pipework.
Upgraded system controls and complete electrical integration.
Minor building modifications to accommodate the modernized plant infrastructure.

Results & Impact:

By transitioning from failing gas infrastructure to a modern, fully electric air source heat pump system, Southfield Hospital has future-proofed its heating capabilities while achieving a 17.59% increase in overall system capacity. The upgraded plant room now operates with vastly improved reliability, lower carbon emissions, and advanced control systems, ensuring a safer, warmer, and more sustainable environment for both staff and patients for decades to come.

2x 54kW Old Boilers Replaced
5 Weeks Delivery Programme
2004 Legacy Plant Retired

Frequently Asked Questions